Contractor Extra Work Authorization Form

Use this contractor extra work authorization form to document added work, price, schedule impact, and client approval before extra work starts.

Use StackQuotes for the approval record

When to use this

Use this form when the client asks for work outside the original scope or field conditions require additional work.

It helps show that extra work was identified, priced, and approved separately from the base proposal.

What to document

  • Original contract or proposal item that does not include the extra work.
  • Description of the extra work and why it is needed or requested.
  • Labor, materials, subcontractors, equipment, and total price impact.
  • Schedule impact and whether the extra work affects other trades or milestones.
  • Client authorization before the contractor starts the extra work.

Printable extra work authorization form

Use this form before extra work starts so the authorization is tied to a specific scope and price.

Job and scope reference

Project name: ______________________________
Original proposal or contract date: ________
Original scope item: _______________________
Extra work requested by: ___________________

Extra work details

Description of extra work: _________________
Reason extra work is needed: ______________
Materials or selections: ___________________
Exclusions: ________________________________

Authorization

Extra work price: $_________________________
Schedule impact: ___________________________
Client authorization: ______________________
Date authorized: ___________________________

Approval boundary

Templates help you write the request. StackQuotes helps you keep the approval record tied to the job.

Extra work authorization example

Extra work
Replace rotten subfloor discovered after demolition.
Not in original scope
Original proposal excluded hidden damage below finished flooring.
Authorization
Client approves $1,450 added price and one additional working day.

CTA

Use StackQuotes when extra work needs to stay connected to the original quote, approval action, and payment record.

How to use this

Use the form as soon as extra work is identified, before crews absorb the change into the base job.

Attach photos, measurements, or selections that explain why the work is extra.

Keep the authorization with the job record and reference it when invoicing the added work.

Approval boundary

Templates help you write the request. StackQuotes helps you keep the approval record tied to the job.

StackQuotes does not guarantee payment or prevent every dispute. It helps contractors preserve the request, pricing context, client action, and job record in one place.

This is general business documentation guidance, not legal advice. For legal disputes, lien rights, or contract enforcement questions, talk with a qualified construction attorney in your state.

Common mistakes

  • Calling work extra without referencing the original excluded or changed scope.
  • Starting extra work while the client is still deciding.
  • Documenting price but not schedule impact.
  • Invoicing extra work without attaching the authorization record.

FAQ

When should a contractor use this authorization form?

Use this form when the client asks for work outside the original scope or field conditions require additional work.

What does it help document?

It helps document changed scope, price or schedule impact, supporting facts, and the client action needed before work continues.

What goes wrong if this is not documented?

The contractor may be left reconstructing scope, price, timing, or approval from memory, messages, and invoices after the job has already moved on.

Is this legal advice?

This is general business documentation guidance, not legal advice. For legal disputes, lien rights, or contract enforcement questions, talk with a qualified construction attorney in your state.